If the decision has been made to acquire software rather
than develop it internally, this decision is normally made
during the:

A. requirements definition phase of the project.

B. feasibility study phase of the project.

C. detailed design phase of the project.

D. programming phase of the project.

Answer Posted / guest

Answer: B

Software acquisition is not a phase in what is regarded as
the standard system development life cycle. However, if a
decision is made to acquire rather than develop software,
this process should occur after the requirements definition
phase and a decision is normally made in the feasibility
study phase.