Explain the OSP cycle?

Answer Posted / sathiyaseelan.p

1. create OSP item in master item

2. define outside processing operation as a resource in the
routing

3. associate the outside resource with a mfg dept , so u can
attach the resource to teh routing.

4. define move transaction with : TO STEP :(queue &
transact)--this will automatically create the pr

5. auto create a po and note the po no,

6. receive the item after outside processing as per the po no.

Is This Answer Correct ?    4 Yes 3 No