Explain the OSP cycle?

Answer Posted / ngopal

OSP - Outside process

Most of the Manufacturing company, they are not doing all
defined process In House except few critical operation for
their products.
Reason is to eliminate the Resource buying cost,
Maintenance cost,Manpower cost and other parameters

OSP Cycle : ( To complete OSP cycle the following need to
be create)
1) OSP Item code
2) OSP Resource
3) OSP department
4) While creating of routing the OSP operation should be
defined and the OSP resources should be attached
Note: UOM should be take care during the creation of OSP
item code and Resource,departments based on the OSP
requirements (Kg,EA,Liter and etc...)
5)discrete Job Creation (manual or through MRP)
6)Move transaction ( Move to OSP Operation)
Note: To Maintain the proper transaction we can assign shop
floor status, the function is to have a control without
doing receiving transaction the user cannot move to next
operation for transaction. it will avoid the error
transaction during the receipt.
7) Once the proper receiving transaction have been done the
shop floor status function allow the component to move next
operation

Here I am explaining only the creation not setup

If you have further doubt ask me.

Regards,nantha

Is This Answer Correct ?    6 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

List out the tables in basic oracle apllication modules?

3176