what is the number of cement bags (50 KG) required for
concreting 1000 Square Feet Slab . Thickness of slab 4 inch.
Answer Posted / ranjith kumar hk
Generally we use M20 for almost concrete works so M20 ratio is 1:1.5:3,for 1m^3 for M20 grade it requires 8 bags of cement ,like wise for above question it becomes 9.3m^3 hence cement bags required are 9.3*8=74.4 approximately 75 bags
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Explain what are the skills required to become an architect?
What is meant by Crystal Concrete?
how to determine H- zone in a column? where it will occur?
Basic questions of civil engineering
What is the origin of name railway sleepers?
what is thumb rule for calculating the size of ISMB required for a particular length of span
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
what is flexible and rigid footing?
Any strength is a stress but any stress is not strength
Thumb rule for steel qty for 1m2 in kg/m2 column slab footing beam
how to stop beam concrete between column
can we make bricks using m10 grade cement concrete and what would be the ratio of raw materials used and price per brick ?
What is thumb rule in quantity and cost estimation of a residential building in civil engineering??
what is pile and deam foundation