how to calculate rate analysis of M25 grade concrete
Answer Posted / br rijal
Solution/ BR Rijal
Volume of dry concrete = 1.54 to 1.57 times volume of wet concrete
so,
calculation for 1 cu.m of concrete works:-
summation of ratio of concrete M25(1:1:2) = (1+1+2) = 4
Shrinkage Factor = 1.55 ( Assumed)
so,
Total volume of wet concrete required = 1.55 cu.m
Now,
Volume of cement required = (1/4)* 1.55 = 0.388 cu.m
= (0.388 / 1440) = 558 kg
cement required = (558 / 50) = 11.16 bags
volume of sand required = (1/4) * 1.55 = 0.388 cu.m
volume of Aggregate required = (2/4) * 1.55 = 0.775 cu.m
Therefore, For 1 cu.m of M25(1:1:2) concrete works;
cement required = 11.16 bags
sand required = 0.388 cu.m
Aggregate required = 0.775 cu.m
Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
what is meant by csr in foundation? what is sbc?what is meant by contour line?
how to disign cuplock shuttering and it's matireal requirement snd any related web site
what is directivity effect?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
what is modular brick and it size
what is the list of building construction equipment & teir output?
how to caliculate required amount of cement and sand required for 1cu.m.
What is fineness modulus ? and its sieve # ?
what is the 0 value in quantity surveying
What is the meaning of soil reinforcement?
what is the effect of duration of earth quake on framed structures ?
How much time Required for PPR pipe network testing
How to take labor charges for construction of 1cum of concrete?
What are the applications of the modulus of elasticity?