how to calculate rate analysis of M25 grade concrete

Answer Posted / br rijal

Solution/ BR Rijal

Volume of dry concrete = 1.54 to 1.57 times volume of wet concrete
so,
calculation for 1 cu.m of concrete works:-
summation of ratio of concrete M25(1:1:2) = (1+1+2) = 4
Shrinkage Factor = 1.55 ( Assumed)
so,
Total volume of wet concrete required = 1.55 cu.m
Now,
Volume of cement required = (1/4)* 1.55 = 0.388 cu.m
= (0.388 / 1440) = 558 kg
cement required = (558 / 50) = 11.16 bags
volume of sand required = (1/4) * 1.55 = 0.388 cu.m
volume of Aggregate required = (2/4) * 1.55 = 0.775 cu.m

Therefore, For 1 cu.m of M25(1:1:2) concrete works;
cement required = 11.16 bags
sand required = 0.388 cu.m
Aggregate required = 0.775 cu.m

Is This Answer Correct ?    3 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

WHAT GOAL DO YOU HAVE IN YOUR CARRIER?

1881


what is meant by csr in foundation? what is sbc?what is meant by contour line?

1833


how to disign cuplock shuttering and it's matireal requirement snd any related web site

2525


what is directivity effect?

1722


how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?

1190






what is modular brick and it size

1177


what is the list of building construction equipment & teir output?

1699


how to caliculate required amount of cement and sand required for 1cu.m.

1747


What is fineness modulus ? and its sieve # ?

717


what is the 0 value in quantity surveying

1932


What is the meaning of soil reinforcement?

668


what is the effect of duration of earth quake on framed structures ?

1813


How much time Required for PPR pipe network testing

1696


How to take labor charges for construction of 1cum of concrete?

690


What are the applications of the modulus of elasticity?

667