Why in India only 50hz frequency not 60hz

Answer Posted / kj

At first each electricity supplier had their preferred voltage (AC or DC) and frequency. Initially 25, 50 and 60 Hz were used. 25 Hz was good for motors but not for lighting as there would be a visible flicker. When electricity became more widespread each country decided to have a voltage and frequency standard. Europe mostly selected 50 Hz and America 60 Hz. India selected 50Hz.
Any type of electrical equipment can be built to use either 50 or 60 Hz. Not as stated in the previous answer "But in America is used advanced equipments only it's operate on 60hz frequency only".

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the circutor?why we use it ?

1835


what is mean by ideal infinite bus? why it is required to consider in fault short circuit calculations?

2240


I am getting above 60 V as open delta voltage against single phase unit ICT at tertiary delta formed and ICT getting trippped on NDR. ICT tested and found in order. PTs provided on tertiary are tested and in order. what may be the reason?

1561


What does bode plots shows?

677


In cable sizing calculation (determining the max route length of cable) why we choose the shortest length between cable length of full load current Iflc & starting current Istart?

2776






please send me the previous year's question papers of jindal GET exams

5518


How to calculate KVA/VA rating of PT or CT from primary & secondary voltage or primary & secondary current?

1989


advantages and disadvantages of inverse definite minimum time RELAY

1059


how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING) I O (current operating)?

1747


Write the force balance equation of m ideal mass element.

719


How to test the Secure Elite 440 Multi function meter working condition.

1614


Why frame of the motor is specified?. If we mention KW and voltage level,automatically frame is decided or separately frame is compulsory to mention?.

1300


I want to merge a cable..in between two metering Cubicals which contains CT's and PT's and Energy meter..before taking merger..what are the common things required?

1132


Why lose 1 phase voltage in 33kv to 415v stepdown transformer

1315


If UG power cable both ends are to be earthed or what? If not why?

1502