ACCOUNTING AND FINANCIAL ENGINEERING - EXAMPLE 34.27 : A biochemical engineering consultancy applies construction accounting in its finance. Its project began on 1 January 2010. Total revenue generated from the project was $9000. On 1 January 2011 as the budget, $2000 had been spent, with $6000 expected. However, the project cost increased latter, causing deviation from its initial budget on 1 January 2012, where $7000 had been spent, with $1400 expected. Let (estimated total cost) = (spent cost) + (expected cost to be spent), (percentage completion) = 100 (spent cost) / (estimated total costs), (total expected profits) = (total revenue) - (estimated total costs). Calculate : (a) total expected profits on 1 January 2011 and 1 January 2012; (b) estimated total cost as and not as the budget; (c) percentage completion of the project since the project began, in the first and second years.

Answer Posted / kangchuentat

ACCOUNTING AND FINANCIAL ENGINEERING - ANSWER 34.27 : On 1 January 2011 (as the budget), estimated total costs = $2000 + $6000 = $8000, total expected profits = $9000 - $8000 = $1000, percentage completion on first year = 100 ($2000 / $8000) = 25%. On 1 January 2012 (not as the budget), estimated total costs = $7000 + $1400 = $8400, total expected profits = $9000 - $8400 = $600, percentage completion on second year = 100 ($7000 / $8400) = 83.33%. Final answer : (a) Profits : $1000 (1 January 2011), $600 (1 January 2012). (b) Costs : $8000 (as the budget), $8400 (not as the budget). (c) Percentage completion : 25% (first year), 83.3% (second year). The answer is given by Kang Chuen Tat; PO Box 6263, Dandenong, Victoria VIC 3175, Australia; SMS +61405421706; chuentat@hotmail.com; http://kangchuentat.wordpress.com.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is it advisable to cool a fin fan by spraying demineralized water on it?

702


How to caliculate the boil up rate, dia and height in both packed and tray distillation columns and any referance books for the design.

2121


What is a quick way to calculate frictional pressure drops in carbon steel pipe?

597


When should one be concerned with the tube wall temperature on the cooling waterside of a shell and tube exchanger?

605


How can you estimate a gas flow based on two pressure measurements?

625






What is a good approximation for the heat transfer coefficient of hydrocarbons inside 3/4" tubes?

677


Explain the factors involved in designing kettle type reboiler?

597


What is the easiest way to extract hydrogen from water and the safest way to store it?

711


What do we use carburizing/nitriding chemicals for?

651


Hi, I want to validate an analytical procedure of a specified impurity, but this impurity is unavailable for me. can I use the API instead of impurity in the linearity test? in Which reference can I find such information?

1323


Explain how can you keep our seawater used for heat rejection clean before entering our heat exchangers?

570


if i added hypo before DM plant so i will affect my resins of anion or cation. if affect it so do prevent what kind of step should be taken to remove hypo before DM inlet?

1076


How can one estimate how the friction factor changes in heat exchanger tubes with a change in temperature?

567


How much will be the increment for postal assistant yearly?

1554


For amonia manufacturing process if pressure, temperature would be increase over optimum level what would be happen?And what steps should be taken?

1749