How to calculate the quantity of brick or mortar in m3.
like in 1m3 brick =....no.
.......mortar=....m3

Answer Posted / sudar

The size of the modular brick is 190 X 90 X 90
Mortar Thickness is 10mm
Assume required brickwork volume is 1 cubic metre (m3)
Volume of bricks with mortar
Volume of 1 brick with mortar = 200 X 100 X 100 ( 10 mm mortar thickness on all sides)

= 0.2 X 0.1 X 0.1

Volume of brick with mortar = 0.002 Cum (m3)

Therefore, Number of bricks required for 1 cubic metre = 1/0.002 = 500 No.s

Volume of bricks without mortar

Volume of 1 brick without mortar = 190 X 90 X 90

= 0.19 X 0.09 X 0.09

Volume of 1 brick without mortar = 0.001539 Cum (m3)

Volume of 500 bricks without mortar = 500 X 0.001539 Cum

Volume of bricks without mortar for 1 cum = 0.7695 Cum (m3)

Therefore,

Required amount of cement mortar = 1 Cum – Volume of bricks without mortar

= 1 – 0.7695

Required amount of cement mortar = 0.2305 Cum (m3) (Wet Condition)
Dry volume of a mortar = 0.2305 cum X 1.33 = 0.306565 cum
We Assume the mortar ratio is 1:6 (1 part Cement & 6 Part Sand = 7 Part)
Required amount Cement quantity in brickwork = 0.306565 X 1/7 X 1440 kg
Required amount Cement quantity = 63 Kg = 1.26 bags (50 Kg bag)
Required amount of Sand = 0.306565 X 6/7 = 0.26277 Cubic metre (m3)

Therefore, For 1 cum of brickwork, we need

500 Numbers of bricks
63 kg of cement
0.263 m3 of sand.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

punj loyed and sapurjl palanjl

1888


Who built the sears tower?

643


why demand factor less then 1 ?

1773


I need old MMUP exam question and answer for Civil engineering

1159


What is the sugested procedure of water purification for public supply?

1723






give me the mix proportion for design mix concrete M 7.5 grade 1:4:8

3612


How do you calculate the power of centrifugal pump?

655


What is the compressive strength of fly ash bricks?

697


Why are the bolts that hold steel rails together in oval holes?

705


What is absolute pressure? How absolute pressure is calculated?

678


how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour

1097


why we provide bent up reinforcement bars at l/4 ? if it is because of diagonal shear , how does it acts ?

2589


how to take concrete quantity for precast segment for viaduct project?

2584


How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance

2433


what values & beliefs have guided you in your career path

2780