I have two AC generators, the first rated 2680KVA for
380V/4345A/pf:0.7 and the second rated 3461KVA for
5500V/363A/pf:0.8. I want to parallel the two generator to
a bus. The second generator passes through a transformer to
down the voltage to 380V and a part of its power goes to
another bus so that it's only a part of the total power of
the second generator taht goes to the considered bus. I
have two Basler DECS100 AVR regulator. How can I make the
synchronization ? What others equipments must have ?

Answer Posted / naseeb jangra

Before doing the parallel Supply both of DG You must Know that:-

Voltage is same

P.F is Same

Frequancy is also same.

This should be done manually or by synchronize the Supply with plc.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Can we use a absolute encoder to show rpm of a motor ? what about the condition when power is off ? what is difference if a incremental one is used ?abanirout@gmail.com

1580


how to introduce yourself

1586


Witch do depand of Power factor and theory of power factor?

1649


If the earth is a good conductor of electricity, why don't people get shocked every time they walking on earth?

1306


1.dg on load alarm/stop alarm... 2.dg on load. piu alarm alarm kaise chek krte hai

1388






Explain forward resistance, static resistance and dynamic resistance of a pn junction diode.

631


i want wipro vlsi placement pattern please send me

1307


what is the affect of earth's magnetic field on the frequency used in aircraft???

1542


Dear sir my name Ankit i m Diploma holder present working in Welspun Corp ltd Anjar as Asst.engg (salary 14400/month ctc) i Would like to change my company also i have selected in ford India pvt ltd Sanand as trainee Tech with salary 12000/month so please suggest me for changing my job hope for *ve response

2423


what shoud be strength and weakness to impress interviewer????????

1622


I have a situation to design sub-Distribution board/Panel meant for feeding power sockets. In the incomer CAN i Take TP MCCB with Neutral Link and All the outgoing feeders with to sockets with TP MCCB and Neutral Link? P.S : My System is IT Earthing

1316


ITI r/tv trade APPLY (J.T.O VACANCEY) ALSO INCLUD AITT ELECTRONIC,WRITEEN XAM DONE 23.03.10 BUT NO RESPONCE WHY ANATHER ID gopal_gh007@rediffmail.com

2949


A commercial Building is designed with 14th floor levels with indoor substation of three phase transformer with rated capacity of 1000 Kva.The transformer delivered 65% of its rated capacity at 0.67 power factor lagging.Because of low power factor, the power customer was penalized and certain cost was charged accordingly based on every point percentage lower than 85%.This situation may repeatedly happen on the succeding energy bills of power customer.The power customer is desired to improve its historical power factor of 0.67 lagging and no further penalty be impose by the local power company on the next bill. Q: Identify the appropriate solution you want to offer to Client?.Justify SCIENTIFICALLY and MATHEMATICALLY the principles behind the solution.

1340


explain the Trip supervision circuit

1658


what about the power of wattmeter at starting and loding?

1655