ENVIRONMENTAL ENGINEERING - QUESTION 22.1 : In order to predict the wastewater production, the population number has to be understood. The population data is : 72000 (for year 1961 or P-1961), 85000 (for year 1971 or P-1971), 110500 (for year 1981 or P-1981). (a) Find the average population increase, or [ (P-1981 - P-1971) + (P-1971 - P-1961) ] / 2. (b) Find the average percentage population increase, or [ (P-1981 - P-1971) / P-1971 + (P-1971 - P-1961) / P-1961 ] / (2) X 100. (c) Find the incremental increase or P-1981 - 2 (P-1971) + P-1961. (d) Let Po = P-1981. After 2 decades or n = 2, the population is P-2001. By using arithmetical increase method, find P-2001 = Po + n (Answer for a). (e) By using incremental increase method, find P-2001 = (Answer of d) + n (n + 1) (Answer of c) / 2. (f) By using geometrical increase method, find P-2001 = Po [ 1 + (Answer of b) / 100 ] ^ n where ^ is power sign, or 1 ^ 2 = 1 x 1 = 1. (g) If the actual P-2001 = 184000, which method of estimation is more accurate, based on your answer in (d), (e) and (f)?
Answer Posted / kangchuentat
ENVIRONMENTAL ENGINEERING - ANSWER 22.1 : (a) Average population increase = [ (110500 - 85000) + (85000 - 72000) / 2 = 19250. (b) Average percentage population increase = [ (85000 - 72000) / 72000 + (110500 - 85000) / 85000 ] x 100 / 2 = 24.025. (c) Incremental increase = 110500 - 2 (85000) + 72000 = 12500. (d) P-2001 = 2(19250) + 110500 = 149000. (e) P-2001 = 149000 + 2 (3) (12500) / 2 = 186500. (f) P-2001 = 110500 (1 + 0.24025) ^ 2 = 169973. (g) Errors of answers : (d) 184000 - 149000 = 35000, (e) 184000 - 186500 = -2500, (f) 184000 - 169973 = 14027. Answer (e) or incremental increase is more accurate to such data, or the most accurate prediction among the three available formulae. The answer is given by Kang Chuen Tat; PO Box 6263, Dandenong, Victoria VIC 3175, Australia; SMS +61405421706; chuentat@hotmail.com; http://kangchuentat.wordpress.com.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How can you estimate the efficiency of a pump?
Can you pls tell me how to calculate the amphere rating of cable in case of three phase supply but all load is single phase
Explain the reasons of removal of particles from effluent gas?
What is a common failure mechanism for above ground atmospheric storage tanks?
What do you understand by wet bulb globe temperature?
Calculate the line size for a cooling water line with a volumetric flowrate of 1200m3/h of water. Density of water = 1000kg/m3
Explain what are the assumptions made on conservation equation?
How much water is lost through a commercial cooling tower system with a throughput of about 600 gpm?
What are the Major Utility Systems in a Pharma Plant? How are they interrelated?
Cooling water line sizing ?
Explain the advantages of using a ball mill over other conventional methods of crushing?
Explain the common failure mechanism for above ground atmospheric storage tanks?
After conducting an internet search for ways to reduce energy costs, I found a recipe for whitewashing that is said to reflect sunlight. The recipe calls for 20 pounds hydrated lime to 5 gallons water to 1-quart polyvinyl acetate. What is a good source of polyvinyl acetate that I can buy at a local store?
Hi, I want to validate an analytical procedure of a specified impurity, but this impurity is unavailable for me. can I use the API instead of impurity in the linearity test? in Which reference can I find such information?
What are some good estimates for heat transfer coefficients for coils in tanks?