Answer Posted / karthik
I guess you wanted to ask for the amount of cement, steel and bricks required for house construction. Although there are no thumb rules, we have derived this by averaging the material consumption for multiple projects.
1. Cement - 400 bags for 1000 sqft
2. Steel - 4000 Kgs for 1000 Sqft
3. Bricks - 5000 Nos for 1000 sqft
We have prepared a detailed infographic on http://www.happho.com/choose-building-materials-estimate-cost-quantities-house-construction/ on this. Since I cannot paste images here, you can check it from there.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
While calculating the weight of the steel per running meter, the formula used is [(dxd)/162]. Why 162 is used in denominator & how it is derived?
How do you calculate the unit weight of concrete?
How to fix the reinforcement in footing shorter bar at bottom and longer fix at top.
How to calculate or what is the process of calculation for making 1Metre squre area by AAC Blok which quantity of Cement, Sand & Chips are to be required?
1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????
could u tell me how to used deform stell bar in reinforce concret?i wanna know the general using in the site!
Are cruise ships built for the transatlantic run?
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
use ofr concrete as per grade ?
How to calculate the cement consumption in RR Masonry in CM 1:8 for the foundation of Ground Level Reservoir
How to calculate brick work quantity?? Block work quantity??
crank types
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.