How Can Calculate Plastering Quantities For 260.04 square meter by using CM 1:4 with 25mm Thick ?
Answer Posted / rrbharathreddy94@gmail.com
Plastering with CM = 1:4
Thickness = 25 mm
Area to be plastered = 260.40 square meter
Thickness of moter layer =25mm=0.025M
volume of moter required =260.40X0.025=6.51 Cum
Add 15 percent of allowences for undualation of surface & wastage = 6.51/100X15=0.976Cum
=6.51+0.976= 7.486 Cum ( total Volume of moter required)
Sand required for 7.486 Cum of CM 1:4= 7.486 Cum
Cement required for 7.486 Cum of CM 1:4= 7.486/4=1.871Cum
Wt of Cement Required =1.871X1440=2694.96 Kg = 2695 Kg (say).
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How can we convert weight batch to volume batch for m30 mix
How to find the cuplock pipe qty in staging for Minor bridge?
Questions related to civil.engg in company
Which stone is best for wall construction Laterite Stone or Cement Blocks
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
Difference between lime, distemper and plastic emulsion?
can i make bricks using M10 grade concrete ? and what would be the cost of a brick if we use m10 grade concrete sand and aggregates ??
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
Spider cracks occur in beam bottom due to––
How to arrive d*d/162 , for finding the kg per meter , wt of steel
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
how to calculate rate analysys of 1:6 plastering 10 sq m
what is modular brick and it size