hi i am working in a civil Lab .....they asked me to find
out the compressive strength of concrete cubes after 7 days
of curing....the value of load on CCT machine is 205KN how
to convert it to Kg/cm2 ....plzz help me...........
Answer Posted / mohd iqbal
205*1000/225
911.11/100
=9.11
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
very simple or less time consuming formula for reinforcement calculation by moment
HOW MUCH STEEL REQUIRED FOR SLAB OF AREA 23'3"*18.3"? FOR SLAB HOW MUCH DIAMETER BAR WILL USE?
what is raft foundation
I need old MMUP exam question and answer for Civil engineering
What is difference between limit state and working stress method? How it is applies in building structure.
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
i am laying a base of dimensions 6.5feet by 7feet by 1.25 feet depth how many bags of 25kg cement and how many bags of 25kg sand will i need
What is GSB gradation
How much cement,sand,bricks and water needed for 1square metre brick work?
How can i do RCC rate analysis?
What is modular elasticity?
Explain what are the skills required to become an architect?