How to calculate cement qty of M10, m20, m25 ?
I got the formula but I lost it.

Answer Posted / shah sohail

M10 IS 1:3:6
Cemnet=1
Sand=3
Agg=6
Wet Dry Cocrete Is 1.52
Total Ratio =1+3+6=10
Cement=1/10*1.52=0.152
Sand=3/10*1.52=0.456
Agg=6/10*1.52=0.912
Cement Is 0.152*1440kg/cum=218kg=4.3Bags
Approx Cement Is 4 Bags.
Sand =0.456cum*35.32cuft/cum= 16cuft
Agg=0.912cum *35.32cuft/cum = 32cuft.

Is This Answer Correct ?    73 Yes 5 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

plumbing CPVC fitting FTE Brass full form

2136


Explain what are the problems one might face while having a Cantilever balcony?

830


what is the minimum cement content for M20 & M25 as per is code -456(2000).

2710


What do you mean by tolerance factor of concrete ?

2673


what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete

3545






how to clculate the %of concrete strenght achive after curing?load

1937


Ratio for 4500 psi concrete

1182


RR masonry rate analysis

2651


Gidc technical que paper

1260


Will water damage concrete?

772


cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate

1212


Scaffolding IS code NO.

1783


As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.

1434


What is meant by scaffolding coefficient?

2192


where i can get material costs on weekly basis

1669