How to calculate cement qty of M10, m20, m25 ?
I got the formula but I lost it.
Answer Posted / shah sohail
M10 IS 1:3:6
Cemnet=1
Sand=3
Agg=6
Wet Dry Cocrete Is 1.52
Total Ratio =1+3+6=10
Cement=1/10*1.52=0.152
Sand=3/10*1.52=0.456
Agg=6/10*1.52=0.912
Cement Is 0.152*1440kg/cum=218kg=4.3Bags
Approx Cement Is 4 Bags.
Sand =0.456cum*35.32cuft/cum= 16cuft
Agg=0.912cum *35.32cuft/cum = 32cuft.
Is This Answer Correct ? | 73 Yes | 5 No |
Post New Answer View All Answers
plumbing CPVC fitting FTE Brass full form
Explain what are the problems one might face while having a Cantilever balcony?
what is the minimum cement content for M20 & M25 as per is code -456(2000).
What do you mean by tolerance factor of concrete ?
what are the strength theories for yeilding and fracture materials. state the theory more suited for 1. mild steel or 2. concrete
how to clculate the %of concrete strenght achive after curing?load
Ratio for 4500 psi concrete
RR masonry rate analysis
Gidc technical que paper
Will water damage concrete?
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
Scaffolding IS code NO.
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
What is meant by scaffolding coefficient?
where i can get material costs on weekly basis