Answer Posted / akram
L/B value is = more than 2 then these slab is Called as one way slab. in this slab the main Reinforcement will be providing in one direction.
L/B value is = Less than 2 then these slab is Called as two way slab. in this slab the main Reinforcement will be providing in both directions.
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is chemical composion test
What is a projection line?
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?
How to decide/consider the grade of bitumen for dbm.
Why should pumping be not used in case of concreting work?
Which prize is the alternative to the NOVEL Prize?
Why the finite element method is lower bound solution?
cause of cylinder test failure
how to calculate the size of triangular ring in rcc column?
why +1 to be followed for calculating the no of bars in BBS. Please explain
Why steel rods are produced only in even dimensions?
What is rate of concrete surface rendering work per sqm
How to determine thee cut length for steel reinforcement bars in R.C.C design
what is tension footing?
What are the steps involved in the concreting process?