How to find quantity of cement bags, sand, coarse aggregate, from 1m3 of concrete of m20 design?
Answer Posted / s k majumder
Meter Cubic wet volume = 1*1.52 =1.52 Meter Cubic dry vol.
= 1.52*35.33=53.70 cft
Hence for M-20 where nominal portion 1.1.5.3
Total volume comes to (1+1.5+3)= 5.5
Therefore Dry volume for one cubic meter.
Cement= 53.70/5.5=cft= 9.76cft= bag= 7.81 bag=8 bags
sand = 9.76*1.5=14.64 cft
stone = 9.76*3=29.28 ct
| Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
how to conversation of all construction material in to brass
plz.show development and anchorage length in simple diagram.
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
sir i want to know that in L & T construction can we do our 6 months training proggramme cum placement???????
What is the bowing depth after stressing of PSC Girder of various spans and various dia of strands?
What is meaning of FREE STANDING STAIRCASE ?
what is the basic difference between Coloumn & Shear Wall
rcc floor to floor 4m. in column reinforcement where we provide lap in exact location.
Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No. Loading Axial force Moment Shear 1 DL+LL 1950 600 20 2 Seismic load 250 4800 700
How can explode a block?
how lap length is increased with increase of Grade of steel?
quantity of material needed for rubble stone masonry for 1:4 and 1:6
how to caluclate sienerge qty in construction in ap
How to plan a project