12 mm dia not available at site for raft, 10 mm are available at site how to calculate?

Answer Posted / mohammed imtiaz

Required Ast/ Cs of area of bar to be provided(10mm).

for ex: no.of bars for T12 = 20nos (Req ast=2261.94sqmm)

No.of bars for T10= 2261.94/78.53
= 29
Hence we can provide 29 nos of T10 instead of 20T12.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why should pumping be not used in case of concreting works?

999


How do you calculate reinforcement weight of steel?

675


Name the main components of a cad gui?

1042


Sir how to find cutting length for footing steel bars in the shape of "u"

1327


how to calculate the concrete mix m30 by volume

1101






In the present situation of ban on mining sand from rivers,can we go for formation of earth dam filters viz;Horizantal sand blanket,inclined chimney and filters under rivetment with crushed rock sand of 6mm down size.If so what are the specifications and is there any codal provision for its authentication?

1502


we have a crushing plant and our product is experiencing flakiness and elongation over limit for granite. what is the solution to this problem? how can it be avoided and what to do differently? It is not ok for batching plants

1775


What is 1/8 on the architect ruler denotes?

654


What is rate for brick masonry work of 1.0 m3 in cm 1:6?

746


at what pressure ply-wood is obtained by gluing wooden sheets

2102


What is the Unit weight of coarse sand (F.M- 2.20) ?????

1428


1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...

1637


how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...

1904


Describe the advantages and disadvantages of using plastic and timber fenders?

674


How to do base isolation using ETABS software?

2488