Mean of m25 concrete

Answer Posted / rudrarup bhattacharjee

If a 15cm side cube is concreted with proper compaction then after 28 days of proper curing its minimum compressive characteristics strength will be 25 Mpa or N/mm2

Is This Answer Correct ?    5 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the per cu. mt. price of ready mix in Gujarat region.?

1780


what is the water-cement ratio of mix design while 30mpa in 7 days?

2623


Difference between pre-tensioning and post-tensioning.

674


kindly mail me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates plz send my email id- VMANDAL91@gmail.com

1395


from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar

4148






Whats the standard thickness of 20'/30' wide rcc service road and what will be the estimated cost per cubit feet

2346


Explain the Strength of brick?

648


I am a civil engineer . I am also selected for sbi clerk interview which is to be held on 4th May2010 is there anybody resembling the same? what question can be asked and what should be the probable answers?

1913


1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

1682


How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57

1496


What are some structures that may be subjected to fatigue?

651


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

1736


Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??

1829


What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?

2386


Tell me about triple point of water.

671