what is the formula for calculating concrete in circular column ? pls explain with diagram add a link for diagram

Answer Posted / ishesh pratap singh

Exmp take 2 m leangth and 300mm dai then
the volume of concrete = 0. 785*D*D*height of column,where D is dai of column

=0.785*0.3*0.3*2=0.141cum

Is This Answer Correct ?    19 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain what are the phases inspections are done by local authority while construction?

737


How to calculate brick work quantity?? Block work quantity??

2107


How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit

5697


How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?

1567


may i know the detailed description of cutting length

1631






What is modular elasticity?

717


Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)

4545


How much quantity water should be placed in one cubic meter area?

891


in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?

1797


natucher of concrete &type of concrete?

1896


can i get civil engineering test papers.......?????

1903


what is Quantity of stone and sand required for one cubic meter of stone work (UCR)

1638


how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.

3325


primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above

1634


What is the difference between undo & redo?

718