what is the formula for calculating concrete in circular column ? pls explain with diagram add a link for diagram
Answer Posted / ishesh pratap singh
Exmp take 2 m leangth and 300mm dai then
the volume of concrete = 0. 785*D*D*height of column,where D is dai of column
=0.785*0.3*0.3*2=0.141cum
Is This Answer Correct ? | 19 Yes | 4 No |
Post New Answer View All Answers
Explain what are the phases inspections are done by local authority while construction?
How to calculate brick work quantity?? Block work quantity??
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit
How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?
may i know the detailed description of cutting length
What is modular elasticity?
Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)
How much quantity water should be placed in one cubic meter area?
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
natucher of concrete &type of concrete?
can i get civil engineering test papers.......?????
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
What is the difference between undo & redo?