how do we calculate the quantity cement,sand, & aggregate
for M20,M15 for 10cum.
Answer Posted / sanket bagade
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how much tempareture are required to make liquid state of pid leed
plz.show development and anchorage length in simple diagram.
WHAT IS THE MAIN DIFFERENCE B/W HIGHWAYS AND MOTERWAYS?
mean of NH4 pipe
How to get MEP technical,instaaltion & testing data for interview?
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
what is the use of water bar in water tank and is this an extra item in estimate?
how to calculate the material from ratio of work PCC, RRM,POINTING, RCC
pls tell me , what is the water content
List out some of the software program that can be useful for architect?
what is difference between GTS bench mark and temporary bench mark
Define What is aggregate?
How to find permissible diagonal tensile stress in reinforced brick work
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
Name the main components of a cad gui?