how to calculate concrete qty for footing using M25 grade
1:1:2 for 731 cft.
Answer Posted / gurubardhan kumar
We have total 735cu.Ft
Ratio of m25= 1:1:2
Now calculate
Cement
1/4x1.54=.385
0.385x1440=554.4kg
554/50=11.08
731/35.314=20.7
20.7x11.08=230 bag
Sand
1/4x1.54=.385
0.385x20.7=7.969cuft
Aggregate
2/4x1.54=0.77
0.77x20.7=15.99cuft
#Ingredient=1.54
| Is This Answer Correct ? | 1 Yes | 2 No |
Post New Answer View All Answers
how can we calculate steel value, depending on load
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
Why is the use of granular sub-base in concrete carriageways not preferred, explain?
how to calculate MR 9(derivation)
what does the grad of cement shows (denotes)?
What are the standard plastic limit/liquid limit/plasticityindex for differrent type of soils?
Define angular dimension?
How to calculate woden area in sft and Cft
what is meant by residual strain?
LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
dialation means
What is OSHA compliance?
What are the responsibilities of a site manager?