Till how many days can we keep a cement bag without using? And on what conditions the cement will get spoiled?
Answer Posted / gobinath
48Days with maxi protect for moisture conditions
Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
how will remove spiderweb cracking in plaster ? what the reasone of make it ?
five requirements of infill panels for walls?
foundation details for 25 ton weight Furnace on 2 supports and 2 tilters
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
any book or article on pumped concrete.
In jack arch floor, the rise is kept?
What is the diff between cad & cadd?
How to calculate quanty of steel in four leg stirrups?
Dear Sir What is the Contraction joint for base Slab
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
In cement concrete how to check a quality of material also proportion of material at site ?
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you