In barbending schedule why is o.42*D is taken. Means why o.42 only???
Answer Posted / arghya das
that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.
Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Detection of a beam & a girder areββββ
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
Formula of mid span bar
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
procedure for preliminary selection of size of column of 5 storey building
Define relative co-ordinates?
what is pouring and explain
How does siphoning work?
how can calculate cutting length of diamond ring
Calculation of Pier Cap with tapper area?
A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.
what is the difference between np2 and np3 concrete mix
Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?