how to calculate weight of round steel bar and square steel bar, i section bar and c channel bar, angle bar
Answer Posted / senthil kubendran
For circular bar = (sq. M of dia of bar)/162 or (dxd)/162 will give weight/meter
For rectangular bar or any shape = (area in sq.M x density in kg/m3) will give weight/meter
Density of carbon steel = 7850 kg/m3
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is the Maximum %age of Steel in columns and beams ?
Explain the Strength of brick?
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
What is packing Factor ?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
What is min thickness,min grade of conc & age of PQC ?
How to cal. The weight of hollow pipe?
door and window wood work calculations and different methods
SAND AND STONE AGGREGATES WASTAGE PERCENTAGE IN CONCRETING WORK?
how much cement and sand required for 1cum rr masonry
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
What is labor and material payment bond?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
What is the difference between one-way slab and two-way slab?