Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to do maint. Of busbar.

Answer Posted / avinit saha

A busbar is a copper plate/bar which is used in main and emergency switchboards to conduct electricity from generators or from one electrical terminal to another. Busbar Inspection and maintenance is carried out by
1.Carryout visual inspection of copper plate and nut bolts. Mark any missing or burn out areas.
2.By hand or using a metal or plastic stick (where access for hand is not possible), tap the bus plates gently so as to make out for any loose connection. Ensure to wear electrical gloves even when bus bar is not live.
3.The busbars are mechanical supported inside the switchboard by means of insulators, which may be of rubber or ceramic materials (bad conductors). Check for any damages in the insulator part.
4.By using an adjustable spanner or particular size spanner, tighten the nuts in the busbar connection for main and emergency switch boards.
5.Check the tightness of the wire connections, which is connected to the circuit breakers.
6.Clean the bus bar and switchboard area with the help of vacuum cleaner.
7.If u find any loose connection or spark, black-out the particular and adjacent bus bar before tightening the nut.
8.If u find any metal piece or nut bolts missing or inside the panel, ensure to remove it as the same can cause short circuit or fire

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

54 Comments Alok and Bhanu play the following min-max game. Given the expression N = 38 + X*(Y – Z) where X, Y and Z are variables representing single digits (0 to 9), Alok would like to maximize N while Bhanu would like to minimize it. Towards this end, Alok chooses a single digit number and Bhanu substitutes this for a variable of her choice (X, Y or Z). Alok then chooses the next value and Bhanu, the variable to substitute the value. Finally Alok proposes the value for the remaining variable. Assuming both play to their optimal strategies, the value of N at the end of the game would be?

2196


Why it is necessary to isolate fire fighting when you are taking shutdown for lv board.

1650


At full load wat is the motor p.f And at no load will is the motor p.f?

2136


dear all i am kumara now current working in electrical designing of control and relay panel i want learn some substaion design then any book are available. pls mention name and authour

1965


what is the meaning of 5% droop or 7% droop in AVR?

2329


How to calculate the size of earth cable to earth the neutral of UPS ?

1952


how to increase senstivity of ct

2435


A TRANSFORMER 440/400V,DELTA/STAR CONNECTED.THE NEUTRAL CONNECTED WITH GROUND CABLE THAT IS DIRECTLY CONNECTED TO THE PANEL,FROM PANEL IT IS CONNECTED EARTH PIT.IS IT RIGHT? IF IT IS RIGHT LEAKAGE CURRENT AFFECTED.SECONDATY IS PROTECTED WITH EARTH LEAKAGE RELAY.

2120


what is meant by LCR meter? where its useful ?

2066


3phase cable calculation formula by motor load

1535


What is A check, B check, C Check & D check for a diesel Generat

2131


what is invertor supply and raw powersupply

2118


Why the arms of delta in a delta-wye power transmission system are kept constant??

1882


how to measure the transformer resistance values(dyn11)?and howmuch the minimum value?

2149


Do closed loop systems require manual input?

1181