When alarm is activated in buccholz relay in transformer

Answer Posted / spl

Depending on the model, the relay has multiple methods to detect a failing transformer. On a slow accumulation of gas, due perhaps to slight overload, gas produced by decomposition of insulating oil accumulates in the top of the relay and forces the oil level down. A float switch in the relay is used to initiate an alarm signal. Depending on design, a second float may also serve to detect slow oil leaks.

If an arc forms, gas accumulation is rapid, and oil flows rapidly into the conservator. This flow of oil operates a switch attached to a vane located in the path of the moving oil. This switch normally will operate a circuit breaker to isolate the apparatus before the fault causes additional damage. Buchholz relays have a test port to allow the accumulated gas to be withdrawn for testing. Flammable gas found in the relay indicates some internal fault such as overheating or arcing, whereas air found in the relay may only indicate low oil level or a leak.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

11000volt DG set carnt kaise banvay

1229


What are the parts in a inverter?

1562


Tell me the reason of connecting domestic t/f primary in star or delta,and also secondary side.

1545


what is difference between earthingpits,earthing grid & earthing mess?

2056


explain different losses in a transformer.

649






what is KSR type transmission tower? What is LSR type transmission tower?

4629


Why do we avoid electrical conduits in floors at apartments?

1621


What is the reason behind current flow(20 A) in amain earth cable of an SMDB? Is cuurent flow(45A etc) through a neutral cable acceptable?

1502


what are all types of cross section in AC cables?

1836


What is transmittance?

638


what is deffrence between squirral cage and wound rotor in IM?

1534


why sielent pole is used only in hydro generators and not in turbo generators

3353


Saving in copper achieved by converting a 2 winding transformer in to an auto transformer is determined by A voltage transformation ratio B load on secondary C quality of core material D size of transformer core

2490


what is the criteria for selecting fuse rating in 1phase, 2phase & 3phase welding sets?

1346


how could we calculate the no of outgoings from a 800 watt distribution board

1259