If a HV Underground Cable (13.8KV) is layed in the ground below 1.5 Mtrs and any building construction is done on the Cable route. IS this allowable or Not? What should be the clearance. As per ISO construction on HV cable route is safe or Not? Why? Can any body suggest the site for my question?

Answer Posted / ra

cables for 13.8 kv is consider to be medium voltage (not HV ) and if it is routed in cable duct so there is no issue.the purpose of cable duct is to provided safety to cable route.
in case if the cable buried in ground, executor of building construction should notify the client through technical query to solve the issue by technical way according to specification and standard.
in my opinion builder suppose to keep opening for cable routing

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

why the pf of semiconductor device is improved the electrical devices

1433


can we do the star delta connection of capacitor for 3- phase motor starter.

1536


The size and construction of bushings in a transformer depend upon?

1167


what is ratio of copper wire size and current ?

1360


What is an ideal transformer?

640






What is mean by Sensitive Earth fault & what are the effects

3739


i am completed diploma in ece,and working in ht and lt lines.so is elligible diploma in ece for get electrical C Licence?plse give ur opinion?

1343


what is advertised hop count

1263


Define what is difference between fuse and breaker?

657


Write the programming software name for LG, SIEMENS,Messung,AB

1531


In EDO ACBs what is a purpose of closing coil and motor, what is the operation of these devices are they inetconnected. means if we give supply to motor and by BCS we charge Closing coil,what exact is operation is and how it charge a spring of ACB. Sir if anybody has an wiring diagram please send me the link to operate and EDO breaker.

1618


Define step response?

641


Is it possible to measure the voltage of a battery from a single terminal?

1230


Who are the manufacturer for Nitrogen based Fire Protectio/explosion prevention for Oil Filled Transformers? India and international both?

1411


I need bhel electrical test pattern & paper

1391