why no deduction for steel is made in the volume of concrete?

Answer Posted / k

Consider a 200x200 column with 4 nos of 20 mm bars.
Total volume of steel: 3.14x0.02x0.02=0.01256
Total volume of concrete= 0.04-0.01256=0.038744
Almost same as 0.04

Is This Answer Correct ?    2 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain what is zoning permit?

769


What are the applications of modulus of elasticity?

770


the distrubution system in water supplies is designed on the basis of avg daily demand peak hourly demand coincident of draft greater of B & C

1577


How to calculate brick work quantity?? Block work quantity??

2112


manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.

1367






Define What is an ice dam sock?

696


what is idealized curve for concrere and steel

1838


what is high type road and low type roads

1192


what is the permanent solution applied for restoration of leaning tower of pisa?

3063


how to reduce size of column 450 x 750 to 230 x.... if it is cut in area of bathroom? means it appears in bathroon any shifting or any other option....building is g + 10 and the bathroom is at first floor...

1899


what is the cost difference of a same structure when it is constructed with brick masonary and when it is constructed with block masonary and concrete as a frame structure????????????????????????

1630


how to find the cement bags and sand requirements for the one square meter of internal,external,ceiling plastering by using the various ratios like 1:3,1:4,1:5,1:6

1022


what is the formula to find the diagonal shape stirrups?

1443


How to arrive the co- efficient of all civil activities? For ex:- painting-enamel in wooden doors. co efficient is 1.8. How this is calculated

1700


what is E VALUE FOR WOOD

1530