how we can calculate the quantity of sand & cement & also
Aggregate so give me to this answer for a slab
Length is : 25' /3.28 = 7.62 Mtr
Width is : 30' /3.28 = 9.14 Mtr
Depth is : 0.6"/3.28 = 0.15 2Mtr
Answer Posted / khadar babu
TOTAL VOLUME:
7.62*9.14*.15=10.44cum
(M15 concrete)
cement required= 10.44*6.48=67.7bags=3384.84Kgs
Sand required= 10.44*0.434=4.54cum
Aggregates required= 10.44*0.868=9.06cum
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.
what is the calculation of raw material for 0.35cum of m-15
Reinforcement details at hinged joint
quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data
what is hydrostatic paradox?
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
what is a well
What is the difference between Hinged and pinned in Column ends
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
What is zoning permit?
what is the difference b/w full length and cutting length?
Slab quantity
what is the hanekom repairing material after concreting work
How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me
How you read 5x3x1 #4 @ 20" 0/C in steel structure?