how we can calculate the quantity of sand & cement & also
Aggregate so give me to this answer for a slab

Length is : 25' /3.28 = 7.62 Mtr
Width is : 30' /3.28 = 9.14 Mtr
Depth is : 0.6"/3.28 = 0.15 2Mtr

Answer Posted / khadar babu

TOTAL VOLUME:
7.62*9.14*.15=10.44cum
(M15 concrete)
cement required= 10.44*6.48=67.7bags=3384.84Kgs

Sand required= 10.44*0.434=4.54cum

Aggregates required= 10.44*0.868=9.06cum

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

An interior designer designed a rack with the given dimensions. The dimensions are in feet. This coplanar frame repeats at every 5feet and constitute a space frame. The total length is 120feet. Which steel member will you suggest? A square bar, A square tube or a circular tube. Explain.

1546


what is the calculation of raw material for 0.35cum of m-15

1033


Reinforcement details at hinged joint

2684


quantity of sand and cement for 10m2 plastering 10mm thick for the ratio of 1:4,1:3and its leabour data

2729


what is hydrostatic paradox?

1701






How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?

1866


what is a well

1500


What is the difference between Hinged and pinned in Column ends

4770


WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10

2302


What is zoning permit?

689


what is the difference b/w full length and cutting length?

1802


Slab quantity 

1601


what is the hanekom repairing material after concreting work

1912


How to calculate the cement plastering for circular and rectangular water storage tanks and how to calculate the area of circular and rectangular floor?? Please help me

1451


How you read 5x3x1 #4 @ 20" 0/C in steel structure?

1064