what is the ratio of M10,M20,M30,M40,M50,M60 grade concrete
Answer Posted / siva
M5-1:5:10;
M7.5-1:4:8;
M10-1:3:6;
M15-1:2:4;
M20-1:1.5:3;
M25-1:1:2;
M30-1:1:3;
Is This Answer Correct ? | 2 Yes | 4 No |
Post New Answer View All Answers
How to get MEP technical,instaaltion & testing data for interview?
Explain the design for rcc multi-storied building?
What is the cost difference between site mix and ready mix concrete per cubic meter
what is the procedure of wet seiving. n percentage of silt in different type of soil?
where will be the reinforcement of slab placed when there is an inverted beam and the bottom of the beam and slab are at same level ?
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
Specific gravity of cement?
What are the phases inspections are done by local authority while construction?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
how clculate excavated or backfilling quantity by simpson's rule
what is kribs is supporting?
Concrete cover for slab, column, beam and footing?
what is the sequence of the activities in the typical under ground water tank including civil & MEP works.
I want to change job.If You have any vacancy please contact me in this mail id-parthamitra086@gmail.com.Myself partha mitra.Diploma in civil engineer with 4+ yrs. exp.Now in kolkata.If you confirm me then I will send my detail resume to you.Also send your mail id to me.My mail id is-parthamitra086@gmail.com.I will be very much thankful to you.
What is Critical path in Ms-Project ?