Answer Posted / piyush singh
Rebaring is the method of insertion of the steel bars when
1) there is change in design or there is some extension of the present structure
2) when Steel rod as per drawing has been not installed and to install the same rebaring is used,
Mostly Hilti chemicals are used for rebaring
Hilti Re-500,
Hilti Hy-150
Is This Answer Correct ? | 23 Yes | 3 No |
Post New Answer View All Answers
can any one give me sample question paper of BHEL at mdansari86@gmail.com as i m appearing for the same exam.
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish
How to calculate canal slope curvature qty!
For the symmetrical continuous beam shown in figure, Prestressed with a force P = 1500 KN along parabolic curve as shown, compute the extreme fiber stresses over the central support for the uniformly distributed load of 24 kn/m. Use load balancing method.
what is difference between GTS bench mark and temporary bench mark
A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
Different sizes of Hollow blocks and its weight. Thanks.
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
what do you understand by M25 concrete
Technical Question of Civil Engineering
why is the column design?
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
Wat is meant by Aecron brick?