what is the relation between the grid voltage and generator
voltage how to link up generator with grid
Answer Posted / muili ibrahim babatunde
This involves synchronization process. Hence, For the two voltages to link, these parameters must be met:
(1)Frequency ( Hz ) : The frequency of the voltages produced by the generator must be equal to grid voltages
frequency.
(2)Voltage ( Volt ) : The line voltages produced by the generator must be equal to the grid line voltages.
(3)Phase Sequence : The phase sequence of the voltages produced by the generator must be same at that of the grid.
(4)phase angle : The phase angle of voltages produced by the generator must be the same with that of grid voltages phase angle. (5) The waveform of the voltages produced by the generator must be the same with that of grid voltage.
Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
what is natural frequency of turbine shaft .
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
why do you consider yourself a suitable candidate for this position
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
How We Calibrate the vaccum transmitter?
What is LB-SR.
What is difference between secondary Air & Tertiary Air and Their use.?
can dp type level transmitter work in under vaccum condition
what is the trip circuit supervision in an electrical meaning?
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
what is the difference between compensated & normal drum level in boiler drum?
what is the basic use of power plant in equipment
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?
How to calculate power press toneage