what are the steps to commissioning a DCS system?

Answer Posted / aswini ku sahoo

1-proper allignment of pannel 
2 power cable laying from UPS DCDB
3-Checking of proper grounding or earthing
4 Negtive terminal of sup. Vol shuold be zero potential.
 and then connect the power cable with proper polarity.
5 U r now almost ready to switch on the pannel but now
one imp thing is to disconnect all AI/AO CARD connector
6 All connector pin should not be sort with the ground.
7 Now swith on the pannel
8 Next UTP cable laying work from DPU TO HMI.
9.Agfter proper connection of UTP ping the system
with priper IP addresss.
10 .now start loop cheching and one by one signal throwing
10.Aftr then one by one 

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

I wnat to practice more online type questions .so will you show them me to take a practice test?

925


How process line mpm calculation is done?

847


principle of automatic votage regulator

1670


DEAR SIR/MADAM MY NAME IS ARKAPROVA BHATTACHARYYA.I AM A FRESHER INSTRUMENTATION ENGINEER.CAN YOU PLEASE SEND SOME QUESTION PAPERS OF GRADUATE ENGINEER TRAINEE EXAM OF DVC(DAMODAR VALLY CORPORATION).MY EMAIL IDs ARE arka_aec@rediffmail.com.

1458


Explain the working principle of lvdt?

699






what are the use of belew gear in general ??

1558


How to calibrate displacer type level transmitter (chemtrol make )for level measurement in hotwell , LP & HP heater ?

5423


what does the ratio 800-400-300-200/1-1-1-1-1 in the specification of current transformer indicates?

2067


why is an oxygen sensor used in a boiler stack

6270


What is offset in a control system.

7955


In dcs panel we are using diff type of modules ?what is module ? what is the use of modules ?diff type of module?

1492


How to erection of DCS Panel at site step by step

995


I have got a call of IOCL interview for projects having 2yrs experience. What sort of questions should I expect in the interview?

1694


Describe a time when you anticipated potential problems and developed preventive measures.

2484


(1) In turbine, what does term CDP, NI, NH, HSSOC, means. (2) What is the purpose of LO overhead tank in turbines.(3) An equipment is certified for EEX, IA, IIC,T6, what do you under stand by this.(4) what is SURGE, and how it is prevented, what is the purpose of bypass valve across AS valve.(5) Give 2 application of quartz crystal used for process parameter measurement.(6) what is meant by cold float of compressor shaft. (7) state four different types of flow measurement. For gas flow measurement mmscfd is the common unit. Expand the unit and specify significance of word S in the unit.(8) what is meant by Gap voltage, in vibration measurement. Normally how much Gap voltage is set and state the reason.(9) what will the new flow factor if D/P transmitter is Re-Ranged from 25” wc to 50” wc.(10) what is the usage of QDV & Volume booster.

3445