At present how many HVDC lines are there in india

Answer Posted / sumit tiwari

1.Back to back at rehand
2.Singrauli- Delhi
3.Ramagundam-Chanderpur
4.Visakhapatnam-Araku
5.Barsoor-Sileru
6.Bihar shariff-Mau

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

If any HVDC line is going with positive & negative(the negative usually have return path of current with earthing electrode). Now the question is if this HVDC earthed electrode which is using as return path and earthed any nearby 400kv or 220kv AC substation equipments. which will be the impact of this on AC substation & its equipment, how severe may be this and what should be the minimum distance require between HVDC earthed electrode and AC substation equipments? It's really an high engineering level question...Dare to answer and increase your knowledge.

1475


Maintenance of transformer???

1812


How can we calculate the transformer rating if the load calculated is 1000KW (11Kv Supply)?

664


There is air in a room . the top and bottom of the room are at constant temp. T1 and T2. DRAW THE temp profiles if a. T1 greater than T2 b. T1 less than T2

1434


In a power conditoining unit (inverter) of a solar plant when we measure the d.c. current fed by different strings of solar plates to inverter, the current in the negative wire is less almost by 1 ampere to the current in its positive wire say current in positive wire 5 A , then current in negative wire of the same string is 4 A. Since the current entering should be equal to current leaving then why the current is noticably less in negative wire.

1143






A mass of 1200g is accelerated at 200 cm/s2by a force. The value of the force required is:(a) 2.4N(b) 2400N(c) 240 kN(d) 0.24N

2153


wat is the first thing dat is needed, 2 lay a cable in some area??

1419


I HAVE A INCOMING 100A MCCB TPN 25KA, CABLE LENGHT OF 80M 70MM CABLE SIZE FROM MAIN SUBBOARD TO NEW DB.BASE ON THE FAULT LEVEL SETTING OF 45KA.I WOULD LIKE TO FIND OUT 25KA ENOUGH KA. APPRECIATE IF SOMEBODY CAN ASSIST ME WITH FORMULA FOR THIS. FRM: JEFF

3524


how can we make cable shedule for controll wiring ? which details must be required for it.?

1649


How do u analyse protection fault when vcb tripping on load

1165


how to calculate units consumption for a 12 hp motor /hr.

1039


hi frnds can any one help me ? plz send me placement paper of IOCL of Electrical streem .... plz send ....its urgent....

1299


A ii kv 1200 A Breaker combination fixed in a cubicle. How many ampere Fuse is required? If fuse is not using, Why?

1511


what is the use of sdf?

1690


Sir, I m 3rd year student 4m DCE and want to do internship in siemens or l&t or any other mnc related to electrical engineering. please tell me the procedure 4 same and oblige me

1525