How we can calculate the quantity of sand, & cement, & also
aggregate for a slab.
Length 25'/3.28 = 7.62 Mtr
width 20'/3.28 = 6.09 Mtr
depth 6" /3.28 = 0.152 Mtr
Answer Posted / selvam.m
First off thank to all ans poster.
Qty Of the Slab is = 7.62X6.09x0.152
= 7.054 Cum
Assume we providing the M20-Concrete on this slab.
Cement:
cement = 7.054*300 = 2116.1kg
or
Cement + Fly ash = 7.054*270 + 7.054*56 = 1904.5 kg cement,395kg fly ash.
Sand:
Sand = 7.054*120*6 = 5078.88 kg.
Aggregate:
20mm= 7.054*126*6 = 5332.824 kg.
12.5mm = 7.054*6 = 3216.624 kg.
Note:
M20-concrete
1Bag - Cement
120kg - sand
126kg - 20mm Agg
76kg - 12.5mm Agg
water - 25 ltr
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to find hardness of water?why it should be determined?
What is the minimum size of the particles of silt soil?
in design case of structural member best suitrable percentage of steel limit is what
How will be cutting in timber plate size 600*400 column size
What is 1/8 on the architect ruler denotes?
How to calculate quantity of plum masonry in 1:3:7
What is kn measurement?
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
Give list of building construction equipment & explain about them in brief. How much is output of JCB, POCLAIN, Steel cutting & bending machine, material hoist, tower crane?
What is the FE 250 structural steel of 8mm tk plate testing sample intervals with IS code or international code?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
How many mortar required for Brickwork of 1 Cu.m works??
What is difference between code and standard and specification?
how much need sand and cement for 1 cft roof construction?
What is semirigid connections?