I have used the proportion of cement:sand:gravel, is 1:2:4.
cement and the sand was provided by the company but i
provided the gravel. this combination was used to fill 500
cubic ft of wall. now i want to know how much gravel was
used in making the wall. can you guys please help me?
Answer Posted / fasil ebrahim
for finding amount of sand used 0.45x500= 225 cft
for gravel 0.9x500 = 450 cft
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
Explain creep?
What happens when water mixed with cowdung is used for priming instead of water for lifting water in pumps?
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
What are the applications of modulus of elasticity?
I need model question papers for writing the Dubai municipality exam,for G+1
Mention what are the composition of a landfill?
Hi.. Can i get hel in finding HPCL previous year question paper? plz help me in finding thiss..
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
Rate analysis of Vitrified tile in cement mortor 1:3
What is binding spacing of the rebars at lapping zones.
How can you distinguish between sorption, absorption and adsorption?
Difference between pre-tensioning and post-tensioning.
what is the use in canals of longitudinal drains and cross drains in lining areas?