Answer Posted / abdullah
if structure is rcc then cement will be 380 kg . means no of
bag is 7.6.
for pcc then cement will be 360kg. means no. of bag is 7.1.
according to this u can find the quantity of water
| Is This Answer Correct ? | 2 Yes | 6 No |
Post New Answer View All Answers
Reinforcement details at hinged joint
How to do rate analysis for concrete work including shuttering work?
what is tension column?
The foundations are placed below ground level, to increase?
What is Grid floor and mention its advantages ?
how calucate cement sand ratio for plstering
how i convert mm into standard wire guage (SWG)no.
crank types
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish
My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).
What are the different methods for drawing an arc?
How much does the leaning tower of pisa lean?
what's the formula for calculate pcc for matt(45mm aggregate)?
How to calculate the crank rod in slab
What is the crank length in the slab?