Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How would you supply power to a village which is very far
from a sub-station and has only a 11k?

Answer Posted / surender kumar singh

As usual Voltage stepping up action is needful.
Level of transformation will be based upon distance between sending end & receiving end.
Slabs of voltage stepping up & down applicable for suitable voltage correction & compensation of line losses to cater power at village.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is meant by IGBT how they differ from tyristor ?

2444


what is kvarh? Please define it With calculation General motors ?

1172


what is the synchronous timer ? and it applications.

2404


WHAT IS THE FORMULA FOR CALCULATING CURRENT RATING(DIRECT IN GROUND OR AIR) OF ARMOURED(XLPE) CABLE OF 4C,16Sqmm?

2105


All tape of electrical questions Answers tape of motor transformer e.o.t crane

2658


what are the standard IR values should be of R-E, Y-E, B-E, R-Y, Y-B, B-R of VCB in closed condition and in open condition for 500KVA & 1000KVA transformers. and what is the acceptable range when tested by 5000V megger.

2340


How to derive detailed design of Suitable bus Bar for 100A for 6.6KV?

1811


how we select ac fuse rating of an power inverter???

1891


1.what is mean by 8/20 micro sec waveshape

2233


what is the formula of starting current of 3phase and 1 phase motor???

2339


I HAVE A 50A MCCB AS PER DESIGN LINE WIRE CONNECT UPWORD SIDE AND LOAD IS CONNECTED TO DOWNWARD SIDE TO THE MCCB.IF NOW ANY ONE CHANGE SUPPLY & LOAD(WISEVERSA) WHAT HAPPENS ? DOES MCCB OPERATION OR WORKING FUNCTION NORMAL IF YES THAN WHY THERE ARE MARKED LINE & LOAD ON MCCB.

2387


what is the question paper model for section engineer in RRB

1903


Why we do 2 types of earthing on transformer (ie:)body earthing & neutral earthing , what is function. I am going to install a oo kva transformer & 380 kva dg set what should the earthing value?

1151


where is core-type and shell-type construction suitable for transformers ?

2098


there is an alternator 480 k.w, 400v,50hz, 4-wire running on load having leakage alternator body earthed current 38 A. is it within acceptable limit? if yes then give reference if no then how to bring within specified limit

1933