200sq.ft of slab and thickness is 6" in that how much cement
are required(bags), sand & aggregates are in cu.m, choose
grade of concrete is m20.

Answer Posted / single ravi

200*.5=100cft/35.32=2.83cum
2.83*6.5=18.39bags
18.35*50=919.75kg of cement required for the given problem

Is This Answer Correct ?    6 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate brick work quantity?? Block work quantity??

2114


What is the release of lien?

697


how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches

1224


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

1581


Can we use concrete of slump cone in cube casting in which we have already measured slump?

1267






What is Critical path in Ms-Project ?

700


how can calculate the compressive strength of concrete cylinder by water cement ratio ?

1235


What is the significance of cost estimate knowledge for an architect?

1153


What is unit weight of roadway layer.. 1.bitumen 2.sand 3.soil 4.concrete 5. aggregate give me some reference for this answers

1850


Describe the various methods of concrete curing?

685


in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft

1508


What is unit weight of normal concrete?

679


Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.

1622


Who name us Engineer & Why?

2031


What are the different types of civil engineering?

652