As per thumb rule cement required per 1 cum of M20 concrete
is 411Kg/cum(1.57/5.5=0.285cum of cement i.e
0.285*1440=411Kg).But as per PWD rate analysis cement
required is 347Kg/cum.the difference is 64Kg.This kind of
difference is coming every grade of concrete.Can you give
perfect suggestion regarding this.
Answer Posted / pranav panchal
This difference comes due to the mix design of the concrete
At every place the mix design depends upon the material & material source so if PWD is considering the cement consumption that means their mix design shows this cement consumption
Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
does a b.tech civil engineer fresher supposed to know how to design rcc structure?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
How to decide/consider the grade of bitumen for dbm.
Explain what is Critical Path Method (C.P.M)?
How to calculate steel for beam slab and column
How many mortar required for Brickwork of 1 Cu.m works??
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.
Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day
The internal dimensions of a wire house 15m*5.6m and the maximum height of piles is 2.70m. What is the maximum number of bags to be stored in two piles ?
What is thumb rule for deep trench excavation
All aptitude question of Bechtel
Why are separation membranes used between concrete pavement slab and sub-base?
What is proportion of PCC Grade G?
Please let me know what is the simplest way of Calculating Mix Designs