What are the steps for Testing of 6.6KV HT Panels?

Answer Posted / c aaron franklin del

1. CT/PT Testing
2. Breaker Testing
3. Control wiring & Interpanel wiring
4. Relay Testing
5. Scheme Check
6. Bus PT and Buscoupler operation check
7. HT Busbar Megger and Hi-pot Test
8. Feeder by Feeder Commissioning

Is This Answer Correct ?    17 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

1.why we are using blocks in withoutgaplightning arrester 2.why we ar using bushing in withoutgap lightning arrestor

1558


Post possible questions for Power Factor Panel FAT / SAT

978


What is the need of earthing transformer for delta side of a transformer. (Think of a line section between a star/delta transformer at a grid substation and delta/star transformer at a village. An earthing transformer is there at the delta side of the star/delta transformer at grid substation). As there are no ground reference there will not be fault current if a one phase is grounded. Further L-L phase will be sensed by the primary side of star/delta transformer as a L-G fault. So why an earthing transformer is required at delta side

975


how to select overload-relay for perticular motor 1.for D.O.L. starter 2. for Star-delta starter ????

2390


How o select the electrical fuse?.What are its characteristics.How to select the material od fuse?

1485






How to calculate the efficiency of Turbo Generator(Alternator) in general....?

2251


how calculated Transformer losses.

1576


What is purpose of reactor?.What is different between line and bus reactor?

1483


WHAT IS THE DIFFERENE IN ACTION OF MCB,MCCB,RCCB

1961


how much LT load can bear by the 100 KW HT connection.

1750


one electromagnet is called

1432


A 7 storey building has a floor area of 35,000sq.ft on each storey. On the ground floor 11KV electrical sub-station is to be erected. A load of 3kw for every 400sq.ft (p.f is 0.8) is proposed for each floor. fire pump 7.5hp, water pump 5hp, lift 2 nos, each 10hp and 20shop load of each shop is 5kw. calculate a. load each floor b. total load of building c. L.T feeders for aech floor and from transformer to main. d. distribution diagram e. capacity of sub-station/capacitor bank f. line diagram

2385


How to arrange a hous hold earthing system to keep minimum earth resistance( below 7ohms).

1723


What happens if i apply 500V to 440V rotary Switch ?

1400


block diagram of 2 ups system connected in parallel mode?

1629