for 100 sqm cement concret (1:2:4) 4cm thick floor,the
quantity of cement required is
Answer Posted / ketan shinde
100×.04=4cu.m of wet concret
To produced 1cu.m of concrte 1.54cu.m of dry concrte required
1.54×4=6.16cu.m
6.16/1+2+4=.88 cu.m of cement reqd.
.88×1440 (densityof cement)=1267.2 kg
Or
1267.2/50kg =25.34=26 bag of cement
Is This Answer Correct ? | 31 Yes | 9 No |
Post New Answer View All Answers
What do you mean by the word 'shear'?
How to produce the Concrete Grade 30mpa at 12hour? How to prevent for plastic shrinkage crack? How can we produce fire resistant concrete?
Difference between lime, distemper and plastic emulsion?
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
What is difference between combin footing & rapt footing
Explain what is the release of lien?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
is there any codal provision for soil cousion over the Hume pipe of Dia 1.2 m.
How much cement and sand are required for 1 square feet of plaster at a thickness of 15 mm at a ratio of 1:4?
What is semirigid connections?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
Why nautical mile is different from statute mile?
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
suppose we have a tendency to make a hole on the surface of the simple supported beam, than where we goes to make it?