Can any body tell me about Hi-pot test, and why it is
necessary and its procedure of testing
Answer Posted / aeccsrpudur
sir
its a high potential test
normally this test is conducted for cables and generator windings
for example if the cable is rated for 11kv and it should with stand 1.25 times of rated voltage during surge conditions
procedure for test - apply dc high voltage 1.25 times gradually and noted the leakage current ,it should be below 100 micro amps for healthy cable for 1 minute
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how we can set the IDMT relay.
How to choose the vector group for the step up and step down transformers??? Tell me the which vector group is suitable for step up and step down transformers and whats the reason to choose and whats the benefits???
what is mean by kneepoint voltage? when it will happen? ( my doubt is, if CT secondary is open means ct get saturation or blas? what are factors are required for calculations? plz give currect anws:
is that any software calculator to calculate the size of cable
in a simple IDMT relay we use neutral point of ct for earth fault then what is the requirement of neutral ct and cbct?
What is meant by a stray loss of a induction motor??? What is the equation to find it
What is the difference between single core 2 wire and single core 3 wire system? Which application we are using this? and for What purpose we are using this?
what is the setting of locked rotor in HT motor ? (answer expecting in percentage)
how to design the heater in temperature control unit to heat 50KL of water?
How to calculate VA rating for CT or PT or Control Transformer?
I am interested to know what does 15 KVA DG set actually means? If I dont know the DG rating, is it possible to identify KW by simply knowing the diesel consumption?
what will be happen if earth point is being used for as a neutral point for raw power , and same will be used for ups earthing
EXPLAIN THE TERMS "INTEREST AND DEPRECIATION" AS APPLIED TO ECONOMICS OF POWER GENERATION.
sir i have cleared the apti test of EIL held on 15th march and my interview will be in new delhi on 2nd june.i will be very much helpful if u help me regarding the type of interview questions comes at EIL.(URGENT.........PLZZZZZZZZZZ...............)
Can anyone provide with a SLD for HT panel installation for a 33KV line and distribution end has three 1.5MV transformers. Is it suitable to use OCB or VCB and also provide me the suitable rating and its connection diagram.