give me the mix proportion for design mix concrete M10 grade
1:4:8
Answer Posted / kumar s
For M-10 grade nominal mix design is 1:3:6
For M-7.5 grade nominal mix design is 1:4:8
As per IS 456:2000, Nominal mix concrete may be used for concrete grades M-20 or lower. Design mix can be arrived with several trial mix design as per guideline proposed in IS 10262:2009. Example my trail design mix for M 10 is 1:3.5:6.10
Hope this will be useful for you...
Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
What is proportion of PCC Grade G?
For submitting the project loan for bank Residential bldg,Suppose we take Provinding RCC mix 1:2:4 for footings No of footings,length ,Breadth,Height ,qty in cum, at last unit/Rate(Rs) ,i would like to know how do we get the unit/Rate
How Can I know the wastages(%) of each work added in estimating the quantity of construction materials?(Eg. Ceiling Work, Brick Work,etc....)
Journal entry Gross salary 10000 Tax 1000 Employee contribution 2000 Employer contribution 2000
Slump Values for works?
can stub column take the load as main column
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.
Permissible wastage of cement as per IS code ? In which IS code I get it?
2nd and 4rt angle elevation used in which country ?
how to find quantity of concrete in PCC M15
WHAT DLC DESIGN IN CONSTRUCTION
Define What is aggregate?
to draw bm diagrams for portal frames under different loadings//
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?