Answer Posted / ratheesh
Clear cover for
Column - 40mm
Beam - 30mm
Slab - 20mm
Is This Answer Correct ? | 5 Yes | 6 No |
Post New Answer View All Answers
How many days should curing of plastering, brick work and concrete
Coverage of 25mm.thick ratio of 1:4 cement mortar?
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
What will be the exam pattern and syllabus for j.e post of haryana staff selection commision? Advt no. (02/2015) Some people says it would only be objective type question papers while others say it would be same as ssc (1 objective,1 conventional) ?? Please answer this question it is needfull to all.
What glue is least sticky?
Permissible wastage of cement as per IS code ? In which IS code I get it?
i have four storeyed rcc building.basement of the building is around 34 years old.it does not have pillar support.it is having lintel steel support at every 7 feet of construction. how long this building will lost long . can any body help me in this regard
How do you calculate the power of centrifugal pump?
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
i want texture painting pwd data
Is it worthwhile to carry out tests on particle density of soil particles for geotechnical design?
contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?
How many square meter can a worker/labor demolish a structure per day?