HOW WE WILL CALCULATE QTY. OF CEMENT,SAND & AGGREGATE
(10MM&20MM) IN Kg.
Answer Posted / achutharaj
we calculate the qty of cement,sand ,aggregate in cu.m,then
we multiple specific weight * qty of cement calculated =
qty in kgs
example 1:2:4
cement specific weight 1440kg/m3
cement qty in cu.m = 0.22
cement qty in kg = 0.22*1440=322kg
sand,aggregate specific weight 1840kg/m3,1550kg/m3
Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
How is make concrete cube?
what is the hanekom repairing material after concreting work
The foundations are placed below ground level, to increase?
What is the quantity of metal 1 & metal 2 to be used in 100 cft concrete?
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
How reactor of SBR installed , is it be over ground, fully under ground or semi sunk ?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
what is Quantity of stone and sand required for one cubic meter of stone work (UCR)
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
How many bricks are there in 100cft?
Explain what is the release of lien?
how to calculate the length diamond shaped striupps in column
What is proportion of PCC Grade G?
on what basis the partial factor of safety are decided? form the load combinations
Explain the difference between slab and beam?