Unit weight of brick? Sand? Aggregate? Steel? Cement? Water?
Answer Posted / mohammed hakeem
Unit weight brick(brick masonry) = 1920 kg/cu.m
Unit weight of brick stone = 2080 to 2700 kg/cu.m
unit weight of sand = 1700 kg/m3
unit weight of aggregate = 1450 to 1550 Kg/m3
unit weight of steel = 7850 kg/m3
unit weight of cement = 1440 kg/m3
unit weight of water = 981kg/m3
Is This Answer Correct ? | 60 Yes | 20 No |
Post New Answer View All Answers
What is the veriplus for ellips card length formula (major axis 3.4m,minar axis 2.6m spacing 0.2m
Bearing capacity of soil determined as per ASTM is to design the foundation size.what is the importance of EV1/EV2 value as per DIN .My consultant ask me to test the the soil as per din to find out this ratio to assess the compacted strength of soil ,,?? is it meaning full ??
Currently my house construction is going on but we just realized that the portico earth beam couldn't connect with the original earth because the beam rod not extended so Please advice
Define polar co ordinates.
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
how many sqft or cft of work done by a mason per day in all works such as brick,block,concrete,shuttering carpenter,reinforcement fabricator,painter,door window carpenter.....everything thank you
for pretensioning which will yield first and same for post tensioning?
what do you mean by yeild stress of a material? What will happen when hit is given to cement?
What is dead load impact load live load
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing
i want texture painting pwd data
what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?
a concrete mix 1 2 4 by volume with water cement ratio as .6 by weight if moisture content in F.A is 6% with 20% BULKING AND IN C.A 1.5% by volume. find quantities of different materials required for one bag of cement
for Precast foundation howmany days required we can shift the foundation with american Standards i need reference with section any body can help
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.