Answer Posted / manoj kumar moharana
cement mortar ratio is (1:5)
assume the area that we are going to calculate the plaster qty is,
L = 3.048 m
B = 3.048 m
given H = 10 mm = 0.01 m
hence the qty is = 3.048 x 3.048 x 0.01 = 0.093 cum
add 30% of the above qty for joints = 0.093 x 0.3 = 0.028
total qty = 0.093+0.028
=0.121 cum
add more 25% for dry volume = 0.121 x 0.25 = 0.03
total qty =0.121+0.03= 0.151 cum
no. of cement bags = 0.151/(1+5) =0.025 cum / 0.0347= 0.720 bags
= 1 apprx.( where as 0.0347 is the volume of 1 bag cement)
qty of sand = 0.025 cum x 5 = 0.125 cum
therefore mortar reqd. for 1:5 cement plaster is
cement = 0.025 cum = 0.720 bag
& sand= 0.125 cum
Is This Answer Correct ? | 28 Yes | 5 No |
Post New Answer View All Answers
List out some of the software program that can be useful for architect?
How much cement,sand,bricks and water needed for 1square metre brick work?
what is the minimum reinforcement provided in beams,footings,slabs? what is the minimum soil bearing capacity to design a multistorey building
How to decide/consider the grade of bitumen for dbm.
What is the biggest dam in america?
How can we demolish concrete beams?
how can calculate the compressive strength of concrete cylinder by water cement ratio ?
significance of specific surface area of particles?
how to calculate weight of 1.8 cum of aggregate
what are the five benefits of using standard terminology in the measurement process?
Which brick is best for construction ,either fly ash or AAC BLOCKS
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
all technical question
why are you joining in this (applied post) job and your aim for this job
pls give me ans to ACT formula cube testing porpuse