i am iti student i have project to do. that IS 100MW
220\33KV SUBSTATION I WANT TO KNOW HOW TO START, LIKE
CALCULATION, WHAT RATING OF CT,CVT, PT, ISOLATOR LIGHTING
ARRESTER WAVE TRAP CIRCUIT BREAKER IN 22OKV SIDE, ALSO TO
WARDS 33KV SIDE PLS HELP ME WITH THIS, THIS MY LIFE NOW, I
KNOW AUTOCAD, I LIKE TO KNOW HOW TO CALCULATE ALL THE THINGS

Answer Posted / surya

i need the calculation methods so i can do it for my self

pls help

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

List the advantages of star-delta starter with induction motor?

619


what is the id1 & id2 setting in differential protection relay of CSPC?

2293


what's the difference between 'shaft power demand' and 'BHP' , when we consider electrical load list.

1089


why US countries maintains 110v and 60HZ

1735


Can 4pole (3 phase+neautral )RCCB proper functioning in only 3 phase load (no neautral, no Earth) ?

1710






What happened if C.T mount at any cable or Bus bar in wrong direction . C.T going on proper work or not . C,T direction is essential thing to properly work.

1255


by using pump duty, how we will can calculate the motor duty(KW)? is there any standard or formula.

1529


it is in our knowledge tht right plug of supply of residential suppy system is phase n other is neutral...howevr the battery charger of mobile works in both ways...i mean it is not restricted in only one direction.ny of the holder of charger can hav phase .so y is it not lik tht phase of supply must b connected 2 phase of charger...?

1567


what is the safety of voltage power transformer(2250KVA0

1555


what is mean by descripiency relay? & wht is its ansi code?

2627


What is the de rating factor of cable? What is the importance of the de rating factor in cable select

1894


How to work definite,over pluxing,revers power,OSR relay

1252


Why do we need a separate control desk & PLC control panel in Boiler plant or coal handling plant? Can we provide cost effective Control desk cum PLC panel. Is there is an specific need for control desk.. kindly advice.

1874


Do any one know exacatly when the results for NHPC held on 8th march 09 for engineering trainees will be released ?. if so please post it, i'm eager to know it.

1694


how to select fuse rating for a 3-phase motor ???

1351