During Load testing of battery charger with temporary AC Generator .When reach 70% load Generator immediately shutdown .we could not able to Recognize ,what is exactly problem .Please kindly clarify us
Answer Posted / binod
AS WE HAVE TWO PART OF THE PROBLEM.
1ST PART IS GENERATOR &2ND PART IS LOAD TESTING OF ABATTERY
CHARGER.
1ST-1) THE GENRATOR IS DTIVEN BY THE ENGINE.
CAPCITY OF ENGINE TO RUN THE GENARATOR FOR DELIVERING ITS
FULL LOAD TO BE CHECKED BY ANY OTHER MEANS. INTERLOCKS OF
TEMPRATURE VARRIATION OF GENERATOR TO ENGINE BE CHECKED.
2ND- CONNECTIONS TO BE VARRIFIED,BATTERY CHARGER
SEMICONDUCTOR ELEMENTS RATING HEALTHYNESS &CAPACITY TO BE
CHECKED.THE LOAD WHICH IS GIVEN TO TEST IS CHECKED IN
INCREASED TEMPRATURE.THE LOAD MAY BE SHORT CIRCUITED AT 70%
CAPACITY WITH INCREASED TEMPRATURE.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
Write the analogous electrical elements in force voltage analogy for the elements of mechanical translational system.
how does it help for selection of a transformer.
what about SAP/MRP regarding manufacturing of electric motors and all drives?
Is there any specialised book to refer about fault level calculation both in MV and LV side??
What is mean 2XWY
ELECTRICAL ENGINEER TEST IN FEWA ANY ONE HAVE KNOWLEDGE ABOUT THIS?????????
What is difference is of VSD,VFD,VSDS, are they the same as the direct current to control dc using above mention
Can we check ELCB constantly from R1 to R8 phase in 1 no DB?
which protection function should measure RMS value of current&DFT value of current?
at what rate the micro controller increment its timer....is it 1micro seconds or 1/(12*10^6) seconds
what is the practical application of full adder circuit?
what id a dry type transformers and its function ?
what is the reqirred voltage in HT motor to get full RPM on no load test?
what is invertor supply and raw powersupply
11 kv input, 66 kv input advantages